- Sputnik International
Asia
Find top stories and features from Asia and the Pacific region. Keep updated on major political stories and analyses from Asia and the Pacific. All you want to know about China, Japan, North and South Korea, India and Pakistan, Southeast Asia and Oceania.

Nepal Pushes Out Indian Firm From Hydropower Project Near Tibetan Border

CC BY-SA 4.0 / UTKHPL / Road tunnel to dam siteLot 1 Civil Contractor of Upper Tamaksohi Hydroelectric Project M/s Sinohydro Corporation Ltd succeeded to breakthrough the project access road tunnel for Dam Site yesterday
Lot 1 Civil Contractor of Upper Tamaksohi Hydroelectric Project M/s Sinohydro Corporation Ltd succeeded to breakthrough the project access road tunnel for Dam Site yesterday - Sputnik International
Subscribe
Amid a delay by an Indian firm in completing hydro-mechanical works at the Upper Tamakoshi Hydropower Plant, Nepal has set a new deadline of December 2018 for the project. Nepal now wants the Indian firm to subcontract the remaining work to an Australian company already engaged in the project.

New Delhi (Sputnik) – The Nepal Electricity Authority (NEA), the state-owned power utility of Nepal, has asked an Indian firm to stop working on the 456 MW Upper Tamakoshi Hydropower Project due to its slow progress. It has asked the Indian contractor to outsource its remaining tasks to another firm reportedly Andritz Hydro of Australia.  

"During a meeting held last week among the Upper Tamakoshi project officials, Andritz Hydro and Texmaco representatives, there was a verbal agreement reached to transfer the remaining work which will be followed by a written agreement soon," Ganesh Raj Neupane, a spokesperson for the Upper Tamakoshi Project, said to local media. 

READ MORE: Nepal’s Upcoming PM Will Have to Balance Between India, China, Say Analysts

In April this year, Nepalese Prime Minister KP Sharma Oli had expressed strong reservations due to delays in the project and instructed the project officials to complete the national project within the given deadline.

Kathmandu, Nepal. File photo - Sputnik International
Asia
Maoist Election Victory in Nepal Could Signal Pivot from India to China
The project was delayed due to the 2015 earthquake and a blockade at the India-Nepal border. The project is now scheduled to start generating power from all units by December 2018. 

READ MORE: China-Nepal Railway May Trigger Indian Response

A senior Nepali official involved in the project told Sputnik that the Indian firm had been intentionally delaying the project to inflate costs, having already crossed the budgeted amount. The project has been financed by the Nepali government from its own internal resources, unlike other externally funded hydroelectric projects. Texmaco officials were unavailable for comment, but bad road conditions in Nepal were early cited as the prime difficulty in completing the project on schedule.

Newsfeed
0
To participate in the discussion
log in or register
loader
Chats
Заголовок открываемого материала