Delivery Delays and Cost Surges Plague US Missile Defense Radar Project

© AP Photo / Mindaugas KulbisMembers of US 10th Army Air and Missile Defense Command stands next to a Patriot surface-to-air missile battery during the NATO multinational ground based air defence units exercise "Tobruq Legacy 2017" at the Siauliai airbase some 230 km. (144 miles) east of the capital Vilnius, Lithuania, on July 20, 2017
Members of US 10th Army Air and Missile Defense Command stands next to a Patriot surface-to-air missile battery during the NATO multinational ground based air defence units exercise Tobruq Legacy 2017 at the Siauliai airbase some 230 km. (144 miles) east of the capital Vilnius, Lithuania, on July 20, 2017 - Sputnik International, 1920, 21.06.2023
Subscribe
Lockheed Martin's new ground radar system, designed to bolster the US missile defense in Alaska, is being hampered by immense delays and cost overruns, raising serious concerns about the project.
Lockheed Martin Corporation is grappling with severe slowdowns in the delivery of its new radar system, an integral part of the broader US missile defense network, according to a report by congressional auditors. The project, conceived to boost the nation's capability to detect and neutralize potential missile threats from adversaries, has been hamstrung by persistent time overruns and spiraling costs.
In a report to congressional committees, the US Government Accountability Office said that "according to the Department of Defense (DoD), potential adversaries are investing substantially in their own offensive missile capabilities and continue to make significant advances. For example, according to the DoD, North Korea continues to develop ballistic missiles capable of threatening the US homeland." This revelation started making its way into various media sources recently.

Severe Setbacks

With COVID-19 disruptions and technical complexities, the project has been delayed by more than four-and-a-half months, incurring $43.7Mln in costs. The Government Accountability Office (GAO) revealed that problems, including a radar component failure, have added nine months to the schedule. This drawback has also postponed a crucial flight test, implying that the radar might be delivered without its capabilities and limitations. In a June 2022 report, 40 major defense acquisition programs weren't on schedule, with more than 29 yet to deliver capacity according to the GAO.
Unforeseen cost surges have plagued the project, originally contracted to be worth $784Mln, forcing the US Missile Defense Agency to shoulder a portion of the financial burden. Despite the government's absorption of $75Mln in cost overruns, industry giant Lockheed Martin finds it is bracing itself for mounting costs. The projected final cost of the project has yet to be revealed by the company, fostering a sense of uncertainty about the eventual cost implications of this project.

MDA Eyes More Spending

Despite shortfalls in planned delivery and testing goals in 2022, the DoD's Missile Defense Agency (MDA) has requested $10.9Bln for the 2024 fiscal year. Furthermore, the MDA is requesting another $55.3Bln for the Pentagon's five-year budget planning period, 2024 to 2028 fiscal years. This predicament highlights the recurrent challenges faced in colossal US military expenditure.