Yamal LNG Project Delayed by Anti-Russian Sanctions - Novatek

© Sputnik / Mikhail Voskresenskiy / Go to the mediabankLNG plant construction in Yamal
LNG plant construction in Yamal - Sputnik International
Subscribe
Novatek Chief Financial Officer Mark Gyetvay said that Major Yamal liquefied natural gas project implementation was postponed due to western sanctions against Russia’s energy sector.

HOUSTON (Sputnik) — Major Yamal liquefied natural gas (LNG) project implementation was postponed due to western sanctions against Russia’s energy sector, Novatek Chief Financial Officer (CFO) Mark Gyetvay said on the sidelines of an international energy conference in Houston, Texas on Wednesday.

"[The sanctions] kind of delayed the initial project terms,” Gyetvay told journalists.

LNG plant construction in Yamal - Sputnik International
Yamal LNG Project Represents Core of Cooperation With Russia - Total CEO
The Yamal LNG project is one of the largest industrial undertakings in the Russian Arctic, and is expected to have a capacity of 16.5 million metric tons of gas a year.

The CFO explained that under the sanctions regime Novatek had to change financing strategy, shifting it from US-based banks to a US-based financial consultancy.

“Some of the project leaders had to leave because they were US-based citizens, I had to step away too," Gyetvay added.

The United States and a number of its allies imposed economic sanctions against Russia in March 2014 following Crimea’s reunification with Russia. The sanctions have targeted Russian individuals as well as the country’s energy, banking and defense sectors.