Boeing KC-46 Air Tanker Delivery Faces More Delays After 1-Year Setback

© Wikipedia / Ken FieldingBoeing KC-46 Pegasus
Boeing KC-46 Pegasus - Sputnik International
Subscribe
A report by GAO reveals that the Air Force's KC-46 modernization program to replace one-third of the aging US aerial refueling fleet, remains more than a year behind schedule with the prospect of additional delays due to air-worthiness certifications issues with the Federal Aviation Administration.

Northrop Grumman, recently awarded the contract for the US’ next-generation long-range strike bomber, was up more than 4.4% at the close of the NYSE Monday. - Sputnik International
GAO Rejection of Appeal Allows Work to Move Ahead on $55Bln Bomber
WASHINGTON (Sputnik) — The Air Force's KC-46 modernization program to replace one-third of the aging US aerial refueling fleet, remains more than a year behind schedule with the prospect of additional delays due to air-worthiness certifications issues with the Federal Aviation Administration, the General Accountability Office (GAO) said in a report on Friday.

"Boeing — the prime contractor — plans to deliver the first 18 fully capable aircraft to the Air Force by October 2018, 14 months later than initially planned. Potential delays in completing flight tests may further delay the delivery of aircraft," the report stated.

The GAO report attributed delays thus far to FAA certification of air refueling pods and postponements of test flights.

Despite falling behind schedule, the KC-46 modernization program is meeting cost and performance targets, the report said.

Total costs have decreased about $7.3 billion, or 14 percent, in the program, which is intended to provide replacements for about one third of the US fuel tanker fleet, the report noted.